Concrete—the Star of the Show

March
2025

We asked Jan Ševčík, the main construction manager of BRESTT STAVBY a.s., the company that is creating Nová Myslivna, how work on it is going.

In December and January, work progressed from the underground floors to the above-ground ones and the structure is slowly but surely gaining in height. “We started working on Nová Myslivna in mid-September 2024 and we should be finished by the end of 2025,” says Jan Ševčík. “The total amount of concrete that the structure will need is roughly 14.500 m³. Our estimate of the total amount of reinforcement is 2,200 tons. We’re currently storing about 4,500 m³ of concrete and 750 tons of reinforcement, which is approximately 30–35% of the total volume,” he adds.

So you're not out of the loop

VIEW ALL NEWS

Construction work in February

In a new video filmed at the construction site, the general contractor’s representative explains what rules builders are adhering to and what steps they take when the temperature drops below zero.
February
2025

Construction work in February

In a new video filmed at the construction site, the general contractor’s representative explains what rules builders are adhering to and what steps they take when the temperature drops below zero.
February
2025

Construction Continues According to Plan Thanks to BIM

The Nová Myslivna project utilizes BIM. What does this really mean and why is it so exceptional?
February
2025

Construction Continues According to Plan Thanks to BIM

The Nová Myslivna project utilizes BIM. What does this really mean and why is it so exceptional?
February
2025

Construction work in December

Despite the winter weather, the concreting of the building's structure is continuing and at the end of December we almost finished the foundation slab.
December
2024

Construction work in December

Despite the winter weather, the concreting of the building's structure is continuing and at the end of December we almost finished the foundation slab.
December
2024

Construction work in November

We focused on our foundation, quite literally. By the end of the month, we were done preparing the ceiling of the 1st floor for concrete layering.
November
2024

Construction work in November

We focused on our foundation, quite literally. By the end of the month, we were done preparing the ceiling of the 1st floor for concrete layering.
November
2024

The call of the wild…

If you're interested in more information, leave us your contact details and we'll get back to you as soon as possible.

I am interested in
By submitting the form, I accept the personal data processing terms of Svoboda & Williams.
* Mandatory
Send
Your message was send
Sending failed. Please try again.