Construction work in December

December
2024

Despite the winter weather, the concreting of the building's structure is continuing and at the end of December we almost finished the foundation slab.

"Even though the weather's been cold recently, our work on the building is continuing according to schedule. People in Brno have noticed that two additional cranes have been added to the site (we currently have four) and for a short time we even had up to five," says Project Leader Tomáš Tschöpl. The four cranes have for now become part of Masaryk Grove's and Kohoutovice's silhouette, which can be viewed from most places in Brno. Each shift at the construction site now numbers fifty workers on average. "Most of the work now consists of formwork, reinforcement, and concreting of the load-bearing part of the building. This entails other types of work such as waterproofing, radon venting, and earthing," adds Tomáš Tschöpl. 


What's almost finished is the foundation slab and builders are already concreting the ceilings of the first underground floor in a section of the future complex. What's emerging therefore is the ground floor of the residential section. "Technology allows us to concrete in cold weather down to five degrees celsius as long as we allow the concrete mix to hydrate before it freezes, which is easy for us to do," explains Tschöpl. 

An invisible yet important milestone is the completion of the sewerage system. A half-kilometer long connecting pipe will divert wastewater from Nová Myslivna to the Šárka Valley.

So you're not out of the loop

VIEW ALL NEWS

Concrete—the Star of the Show

We asked Jan Ševčík, the main construction manager of BRESTT STAVBY a.s., the company that is creating Nová Myslivna, how work on it is going.
March
2025

Concrete—the Star of the Show

We asked Jan Ševčík, the main construction manager of BRESTT STAVBY a.s., the company that is creating Nová Myslivna, how work on it is going.
March
2025

Construction work in February

In a new video filmed at the construction site, the general contractor’s representative explains what rules builders are adhering to and what steps they take when the temperature drops below zero.
February
2025

Construction work in February

In a new video filmed at the construction site, the general contractor’s representative explains what rules builders are adhering to and what steps they take when the temperature drops below zero.
February
2025

Construction Continues According to Plan Thanks to BIM

The Nová Myslivna project utilizes BIM. What does this really mean and why is it so exceptional?
February
2025

Construction Continues According to Plan Thanks to BIM

The Nová Myslivna project utilizes BIM. What does this really mean and why is it so exceptional?
February
2025

Construction work in November

We focused on our foundation, quite literally. By the end of the month, we were done preparing the ceiling of the 1st floor for concrete layering.
November
2024

Construction work in November

We focused on our foundation, quite literally. By the end of the month, we were done preparing the ceiling of the 1st floor for concrete layering.
November
2024

The call of the wild…

If you're interested in more information, leave us your contact details and we'll get back to you as soon as possible.

I am interested in
By submitting the form, I accept the personal data processing terms of Svoboda & Williams.
* Mandatory
Send
Your message was send
Sending failed. Please try again.