Construction work in October

October
2024

The foundation is the most important thing, and we’ve finished drilling and filling 220 posts with concrete. This is what Nová Myslivna will stand on. A quarter of the foundation slab is completed, and we’re working intensively on its remaining section.

Big changes also happened on the first basement floor, where the utility facilities pertaining to the wellness center have been installed. After careful waterproofing, we’re now fortifying this space. Another thing we’re currently working hard on is the precise placement of waste infrastructure.

Thanks to the amazing weather this month, construction work has been progressing by leaps and bounds. Here are the latest facts and figures fresh from the Nová Myslivna construction site.

220 posts
We drilled and filled with cement 220 foundation posts on which Nová Myslivna will stand. We took great care with the building’s foundation since we were dealing with very hard ground.

3,000+ m3 soil
Before Nová Myslivna can rise up, we needed to start underground. To get ready for construction, we removed over 3,000 m3 of soil.

45 people
This is the number of people who come to work at Nová Myslivna on a daily basis. Workers are currently focusing on the foundation slab and on the utility shaft for the future wellness zone.

2 cranes
We’ve temporarily changed Brno’s panorama. Two tall cranes now tower over Nová Myslivna, and two others will be added at a later date.

24 months
This is the amount of time we have to finish Nová Myslivna. In fall 2026, we’ll be handing over the first apartments to their new owners so they can enjoy the most beautiful views in Brno.

So you're not out of the loop

VIEW ALL NEWS

Construction work in November

We focused on our foundation, quite literally. By the end of the month, we were done preparing the ceiling of the 1st floor for concrete layering.
November
2024

Construction work in November

We focused on our foundation, quite literally. By the end of the month, we were done preparing the ceiling of the 1st floor for concrete layering.
November
2024

Geological work

Work is underway at the Nová Myslivna construction site on the foundations of the building under the supervision of geologists and structural engineers.
September
2024

Geological work

Work is underway at the Nová Myslivna construction site on the foundations of the building under the supervision of geologists and structural engineers.
September
2024

1st Sales Phase Launched

Svoboda & Williams is launching the sale of the exclusive apartments in the Nová Myslivna residential project. This first rollout includes 26 units to choose from, with layouts ranging from studios to spacious penthouses.
June
2024

1st Sales Phase Launched

Svoboda & Williams is launching the sale of the exclusive apartments in the Nová Myslivna residential project. This first rollout includes 26 units to choose from, with layouts ranging from studios to spacious penthouses.
June
2024

Construction Has Started

The construction of the Nová Myslivna residential project was inaugurated by the symbolic tapping on the foundation stone by the representatives from INFINITY estate.
May
2024

Construction Has Started

The construction of the Nová Myslivna residential project was inaugurated by the symbolic tapping on the foundation stone by the representatives from INFINITY estate.
May
2024

The call of the wild…

If you're interested in more information, leave us your contact details and we'll get back to you as soon as possible.

I am interested in
By submitting the form, I accept the personal data processing terms of Svoboda & Williams.
* Mandatory
Send
Your message was send
Sending failed. Please try again.